Technology Railway Electrification Status
Railway Electrification Status – Indian Railways (Technology Section)
1. Overview
- Vision: “Net-Zero Carbon Emitter” by 2030
- Electrification is the backbone of energy security, higher haulage capacity & 25 % savings in operating cost.
- Implemented by: CORE (Central Organisation for Railway Electrification) – HQ at Allahabad (Prayagraj), set up in 1961.
2. Key Statistics (as on 31.03.2024*)
| Parameter | Figure |
|---|---|
| Total Route km of Indian Railways | 68,438 km |
| Broad-Gauge (BG) route km | 65,436 km |
| Electrified BG route km | 60,081 km |
| % BG route electrified | 92 % |
| Running track km electrified | ~88,000 km (≈90 %) |
| Traction substations (TSS) energised | 6,790 nos. |
| States/UTs 100 % electrified | 19 |
| Target for 100 % BG electrification | 2023-24 (achieved) |
| Energy saved per annum | ~2,500 crore ₹ |
| CO₂ reduction | ~4 million t/year |
*Source: CORE Monthly Bulletin & Railway Board Statement, April 2024.
3. Zone-wise Electrification Snapshot (BG route km)
| Zone | Total BG RKM | Electrified RKM (31.03.24) | % |
|---|---|---|---|
| Central (CR) | 4,528 | 4,528 | 100 |
| Eastern (ER) | 2,833 | 2,833 | 100 |
| East Central (ECR) | 3,478 | 3,478 | 100 |
| East Coast (ECoR) | 2,835 | 2,835 | 100 |
| Northern (NR) | 7,525 | 7,525 | 100 |
| North Central (NCR) | 3,544 | 3,544 | 100 |
| North Eastern (NER) | 3,352 | 3,352 | 100 |
| Northeast Frontier (NFR) | 4,227 | 3,870 | 91.5 |
| North Western (NWR) | 5,592 | 5,592 | 100 |
| Southern (SR) | 5,143 | 4,965 | 96.5 |
| South Central (SCR) | 6,204 | 6,204 | 100 |
| South Eastern (SER) | 2,949 | 2,949 | 100 |
| South East Central (SECR) | 2,765 | 2,765 | 100 |
| South Western (SWR) | 3,660 | 3,660 | 100 |
| Western (WR) | 6,182 | 6,182 | 100 |
| West Central (WCR) | 4,611 | 4,611 | 100 |
| Total BG | 65,436 | 60,081 | 92 |
4. Milestones & Chronology
| Year | Event |
|---|---|
| 1925 | First 1.5 kV DC section – Bombay VT–Kurla (Great Indian Peninsula Railway) |
| 1957 | Decision to adopt 25 kV 50 Hz AC (French SNCF system) |
| 1960 | Rajkharsawan–Dongoaposi (SER) first 25 kV AC trial section |
| 1961 | CORE created |
| 1967 | First AC loco (WAG-1) commissioned |
| 1995-96 | Calcutta (Sealdah)–Delhi Rajdhani route electrified |
| 2014 | 23,541 km electrified (34 % network) |
| 2017 | 100 % electrification of Konkan Railway |
| 2020 | Hundred-percent electrification of entire South Central Zone |
| 2021 | All routes in Jammu & Kashmir (USBRL) up to Baramulla energised |
| 2022 | Last diesel-only trunk route – Gondia–Ballarshah (SECR) – switched over |
| 2023 | 100 % electrification of BG network declared achieved |
| 2024 | Focus shifted to doubling/3rd line electrification & TSS augmentation |
5. Technical Standards
| Item | Specification |
|---|---|
| Traction voltage | 25 kV AC, 50 Hz, single phase |
| Catenary type | 150 mm² Cu-Ag (OHE) & 107 mm² Cu Mg alloy (catenary) |
| Normal OHE height | 5.50 m above rail level (5.30 m for goods loops) |
| Max. Permissible speed under OHE | 160 km/h (BG); trials for 200 km/h under way |
| Power block norm for electrification | 6 h/day (traffic block) |
| Remote monitoring | SCADA (Supervisory Control & Data Acquisition) at all TSS |
6. Production Units & Electrification Assets
| Unit | Location | Product/Role |
|---|---|---|
| CLW | Chittaranjan | Electric locos (WAG-9, WAP-7) |
| BLW | Banaras (Varanasi) | Electric locos (WAP-5, WAG-12B) |
| ICF | Chennai | EMU/MEMU coaches |
| RCF | Kapurthala | EMU/MEMU coaches |
| CORE | Prayagraj | Planning & execution of electrification projects |
| RVNL | New Delhi | Project implementing agency (PIA) for many electrification works |
7. Benefits of Electrification (Exam points)
- 25-30 % reduction in operating cost (no diesel haulage).
- 25 % more haulage capacity – higher axle-load & speed.
- Regenerative braking in 3-phase locos saves 10-15 % traction energy.
- Environmental: 1 kWh electric traction emits 0.83 kg CO₂ vs 1.2 kg for diesel.
- Import substitution: saves 3,000 crore ₹ forex on diesel every year.
- Unified 25 kV system allows through-running of trains without loco change (e.g., Howrah–Mumbai via Rajdhani).
8. Frequently-Asked Theory Bits
Question:01 Which organisation, headquartered in Prayagraj and established in 1961, is responsible for railway electrification in India?
A) RDSO
B) CORE
C) RITES
D) IRCTC
Show Answer
Correct Answer: B
Explanation: CORE (Central Organisation for Railway Electrification), established in 1961 with its headquarters at Prayagraj, handles all railway electrification projects across Indian Railways.
Question:02 What is the standard voltage & frequency adopted by Indian Railways for traction?
A) 25 kV AC, 50 Hz, single phase
B) 15 kV AC, 50 Hz, single phase
C) 25 kV DC, 50 Hz, single phase
D) 25 kV AC, 60 Hz, single phase
Show Answer
Correct Answer: A
Explanation: Indian Railways uses 25 kV AC at 50 Hz in a single-phase system for electric traction to balance power transfer efficiency and infrastructure cost.
Question:03 Name the first section converted to 25 kV AC in India.
A) Rajkharsawan–Dongoaposi (SER)
B) Howrah–Burdwan (ER)
C) Mumbai Central–Virar (WR)
D) Chennai Beach–Tambaram (SR)
Show Answer
Correct Answer: A
Explanation: The Rajkharsawan–Dongoaposi section of the South Eastern Railway was the first in India to be electrified at 25 kV AC, commissioned during 1960-61.
Question:04 Which Indian Railway zone was the first to achieve 100 % electrification of its route?
A) South Central Railway
B) Western Railway
C) Central Railway
D) Northern Railway
Show Answer
Correct Answer: A
Explanation: South Central Railway (SCR) was declared the first fully-electrified zone in 2020.
Question:05 [As on 31.03.2024, what percentage of the total Broad-Gauge route km had been electrified?]
A) 78 %
B) 85 %
C) 92 %
D) 97 %
Show Answer
Correct Answer: C
Explanation: Out of 65,436 km of BG route, 60,081 km had been electrified by 31.03.2024, which is ≈92 %.
9. Quick-Fire Tables for Last-Minute Revision
A. States 100 % electrified (19)
- Andhra Pradesh
- Telangana
- Tamil Nadu
- Karnataka
- Kerala
- Maharashtra
- Gujarat
- Rajasthan
- Punjab
- Haryana
- Delhi
- Uttar Pradesh
- Uttarakhand
- Himachal Pradesh
- Bihar
- Jharkhand
- West Bengal
- Odisha
- Chhattisgarh
B. Remaining non-electrified sections (≤ 8 %)
Mainly in Northeast (NFR) & some under-gauge-conversion projects in hill/NE regions.
10. Practice MCQs – Railway Electrification Status
-
The headquarter of CORE is located at
A. New Delhi
B. Mumbai
C. Prayagraj
D. Kolkata
Answer: C -
As on 31.03.2024, approximately what percentage of BG route km has been electrified?
A. 82 %
B. 88 %
C. 92 %
D. 98 %
Answer: C -
Indian Railways adopted which traction system for new electrification projects?
A. 1.5 kV DC
B. 3 kV DC
C. 25 kV AC 50 Hz
D. 15 kV AC 16⅔ Hz
Answer: C -
The first 25 kV AC trial section in India was
A. Howrah–Burdwan
B. Rajkharsawan–Dongoaposi
C. Igatpuri–Bhusaval
D. Chennai–Gummidipundi
Answer: B -
Which of the following zones has NOT yet achieved 100 % electrification?
A. SCR
B. NFR
C. WR
D. ECR
Answer: B -
The total number of traction substations (TSS) energised on Indian Railways is about
A. 4,590
B. 5,400
C. 6,790
D. 8,100
Answer: C -
The nominal height of OHE contact wire above rail level for BG is
A. 4.80 m
B. 5.50 m
C. 6.10 m
D. 6.45 m
Answer: B -
Which organisation executes electrification projects on behalf of Railways?
A. RPF
B. RVNL
C. CONCOR
D. DFCCIL
Answer: B -
The energy saving achieved through regenerative braking in 3-phase electric locos is around
A. 3-5 %
B. 10-15 %
C. 25-30 %
D. 40-45 %
Answer: B -
The first electric train in India ran in 1925 on
A. Bombay VT–Kurla
B. Madras Beach– Tambaram
C. Sealdah–Bardhaman
D. Howrah–Burdwan
Answer: A -
By which year has Indian Railways targeted to become a “Net-Zero Carbon Emitter”?
A. 2025
B. 2027
C. 2030
D. 2035
Answer: C -
Which state became the latest to achieve 100 % rail route electrification (2023)?
A. Assam
B. Manipur
C. Jammu & Kashmir
D. Sikkim
Answer: C -
The approximate CO₂ reduction per year due to electrification is
A. 1 million t
B. 2 million t
C. 4 million t
D. 8 million t
Answer: C -
The decision to adopt 25 kV AC system was taken in the year
A. 1950
B. 1957
C. 1965
D. 1970
Answer: B -
The cost of electrification per route km (2022-23 average) is roughly
A. 0.5 crore ₹
B. 1 crore ₹
C. 1.5 crore ₹
D. 2 crore ₹
Answer: B
Last-Minute Cram Card
- 92 % BG network electrified (60,081/65,436 km)
- 25 kV AC 50 Hz – standard
- CORE – Prayagraj – 1961
- First 25 kV section – Rajkharsawan–Dongoaposi
- Regenerative braking – 10-15 % energy saved
- Target 100 % electrification – achieved 2023-24
- Net-Zero target – 2030