Track Machines

Track Machines – Complete Railway GK Capsule

1. What are Track Machines?

Track machines are self-propelled or attachable railway vehicles designed to perform specific maintenance, renewal or inspection tasks on the track structure so that manual labour is reduced, accuracy is improved and traffic blocks are minimised. Indian Railways owns the world’s largest fleet of on-track plant (OTP) – more than 7,000 units.


2. Broad Categories (as per Indian Railways’ “Permanent Way Manual 2022”)

Category Typical Speed (working) Power Main Tasks
Tamping Machines 0–2.5 km/h 1,000–1,800 hp Packing, aligning, leveling, stabilising
Ballast Cleaning Machines (BCM) 0–600 m/h 1,200–1,600 hp Screening & restoring clean ballast
Ballast Regulating Machines (BRM) 0–10 km/h 400–600 hp Profiling, shoulder cleaning, boxing
Dynamic Track Stabiliser (DTS) 0–2 km/h 400–600 hp Post-tamping consolidation
Rail Grinding Machines (RGM) 3–20 km/h 1,200–1,500 hp Rail profile correction, fatigue removal
Switch Grinding Machines (SGM) 1–8 km/h 800–1,000 hp Turnout grinding
Rail Flaw Detection Cars (USFD) 30–40 km/h Dual-mode (DEMU) Ultrasonic internal flaw detection
Track Recording Cars (TRC) 100–180 km/h Self-propelled Geometry recording, video-imaging
Flash-Butt Welding Plants (FWP) Stationary 400–600 kVA Factory / site welding of LWR/CWR
Mobile Flash-Butt Welding Units (MFW) 20–80 km/h (travel) 400 kVA Field welding, short-possession blocks
Portal / Material Handlers 0–5 km/h 300–400 hp Sleeper / panel replacement
Rail Head Profile Milling Train 0–1.5 km/h 1,000 hp Precision milling (0.2 mm accuracy)

3. Technical Specifications (Latest IRS & RDSO Circulars)

  • Tamping Machine (09-3X model)

    • Tamping banks: 3 × 16 tools (48 tools)
    • Working radius: ±2.5 m from track centre
    • Lifting range: 150 mm; aligning range: ±150 mm
    • Computer: ALC / GVA-3 system with 10 m chord versine calculation
    • Output: 650 m/h (plain track) / 250 m/h (turn-out)
  • Ballast Cleaning Machine (RM-80)

    • Excavating chain width: 3,350 mm
    • Screening capacity: 650 m³/h
    • Ballast reclaim: 95 % of reusable stone
    • Minimum curve radius negotiable: 150 m
  • Dynamic Track Stabiliser (DGS-62N)

    • Vertical exciting force: 2 × 310 kN @ 35 Hz
    • Settlement achieved: 15–25 mm in 2–4 passes
    • Allows 50 % speed restriction relaxation immediately after tamping
  • Rail Grinding Machine (RGM-20)

    • Grinding stones: 96 (20-stone modules)
    • Metal removal: 0.1–0.3 mm/pass
    • RMS surface finish: ≤10 µm
    • Grinding angle: ±70° (gauge / field side)
  • USFD Car (Mini-TRC)

    • Probe frequency: 0°, 37°, 70° (4 MHz)
    • Test speed: 40 km/h max; defect resolution: 2 mm
    • GPS tagging accuracy: ≤1 m

4. Historical Milestones

Year Event
1956 First 2 tampers (Jackson type) imported by IR under IInd Five-Year Plan
1964 RDSO issues first “Specification for 08-16 plain-track tampers”
1972 Indigenous manufacture started at BEML, Bengaluru (collab. Plasser & Theurer)
1986 First BCM (RM-80) commissioned on SER
1990 Introduction of computer-aided tamping (ALC) on Rajdhani route
1995 First CSM (Continuous Action Tamping) Machine – 09-32 CSM
2007 Launch of “Mission Track” – target 2,500 tampers by 2020
2012 First DTS (Plasser 62 N) used prior to 160 km/h trial of Semi-High Speed
2016 IR contracts 188 new machines (₹2,300 cr) under “Track Machine Procurement-17”
2018 RDSO approves indigenised “Make-in-India” 09-3X tamper by BEML
2020 First rail-milling train imported (Linsinger, Austria) – deployed on WCR
2022 Highest-ever allocation ₹3,992 cr for track machines in Pink Book

5. Present Fleet & Deployment (as on 31-03-2023)

Machine Type Holding (IR) Zone with Max Nos Avg. Age (yrs)
Tampers (Plain + UNO) 1,420 CR (192) 14
BCM 210 SER (38) 18
DTS 102 NR (22) 9
RGM (main-line) 42 NR/WR (10 each) 12
USFD cars 61 NCR (11) 11
TRC/SRC 29 NR (6) 15
  • Vision-2024 target: 1 tamper per 125 km of track (present 1:152 km)
  • Outsourcing: 30 % of annual tamping output now done by private machines under “MMO” contracts (Machine-Mode-Output)

6. Recent Policy Updates (2021-23)

  1. Automatic Block Prohibition (BPAC): tamper/DTS block automatically approved in ICMS (Integrated Crew Management System) – no manual TRR required.
  2. Green Initiatives: Stage-IIIA (Euro) diesel engines & bio-diesel blend up to 20 % (B-20) mandated for new machines.
  3. IoT-enabled telematics: GPS/OBC data uploaded to “Raksha Kavach” cloud portal for real-time machine monitoring.
  4. Indigenous “Vande-Metronom” TRC: jointly developed by RDSO & BEML – 180 km/h self-propelled – rolled out Jan 2023.
  5. Rail-Milling technology: approved for 3 more zones (NCR, ER, SCR) in 2023-24 – tender value ₹1,080 cr.

7. Safety & Standards

  • IRS:T-39/2019 – General & safety requirements for OTP
  • Minimum crew: 4 (driver, operator, maintainer, lookout)
  • Maximum gradient on which machine can work: 1 in 40 (caution) & 1 in 100 (normal)
  • Brake system: Dual (air & parking), fail-safe, spring-applied
  • Fire-extinguisher: 6 kg DCP × 4, validity 3 yearly
  • First-aid & oxygen cylinder: mandatory for BCM (confined-space work)

8. Quick-Fire Data for Exams

  • Tamping tools material: Hadfield steel (12 % Mn)
  • Ballast shoulder slope maintained by BRM: 1 in 1.5
  • USFD probe angle for bolt-hole crack detection: 37°
  • Minimum rail temp. for flash-butt welding: < 600 °C of rail
  • DTS operation forbidden when ambient temp.: > 50 °C (rail stress hazard)
  • Rail-grinding stone composition: Aluminium oxide + resin bond
  • IRS coach under-gear clearance: 65 mm (for TRC/SRC)

9. 15+ FAQs (With Answers)

  1. Which of the following machines is used for consolidating freshly tamped track? A) BCM B) DTS C) RGM D) USFD

    Show Answer Correct Answer: B Explanation: The Dynamic Track Stabiliser (DTS) is specifically designed to consolidate the ballast bed immediately after tamping operations.

  2. The first tamping machines were imported by Indian Railways in A) 1951 B) 1956 C) 1961 D) 1965

    Show Answer Correct Answer: B Explanation: Indian Railways began importing initial track maintenance machines, including tamping machines, in 1956.

  3. Screening capacity of RM-80 BCM is approximately A) 150 m³/h B) 350 m³/h C) 650 m³/h D) 950 m³/h

    Show Answer Correct Answer: C Explanation: The RM-80 Ballast Cleaning Machine has an approximate screening capacity of 650 cubic metres per hour.

  4. The minimum curve radius negotiable by RM-80 ballast cleaning machine is A) 90 m B) 120 m C) 150 m D) 200 m

    Show Answer Correct Answer: C Explanation: The RM-80 BCM is designed to operate on curves with a minimum radius of 150 metres.

  5. ALC system in modern tampers stands for A) Automatic Level Controller B) Analogical Lifting Computer C) Automated Lining Computer D) Analog Loop Control

    Show Answer Correct Answer: B Explanation: ALC stands for Analogical Lifting Computer, which controls the lifting mechanisms in modern tamping machines.

  6. Dynamic Track Stabiliser applies vertical exciting force at a frequency of about A) 15 Hz B) 25 Hz C) 35 Hz D) 45 Hz

    Show Answer Correct Answer: C Explanation: The DTS applies vertical vibration at a frequency of approximately 35 Hz to achieve effective ballast consolidation.

  7. Which machine is deployed to rectify rail surface corrugations? A) DTS B) BCM C) RGM D) TRC

    Show Answer Correct Answer: C Explanation: The Rail Grinding Machine (RGM) is used to remove surface defects and corrugations from the rail head profile.

  8. The indigenous 09-3X tamper has been developed by A) BHEL B) BEML C) DMRC D) Texmaco

    Show Answer Correct Answer: B Explanation: BEML (Bharat Earth Movers Limited) is responsible for the indigenous development and manufacturing of the 09-3X tamping machine.

  9. IRS:T-39/2019 deals with safety requirements of A) Loco pilots B) Track machines C) Signalling gears D) Wagons

    Show Answer Correct Answer: B Explanation: The IRS:T-39/2019 specification outlines the safety requirements and standards for track maintenance machines.

  10. Stage-IIIA engines used in new track machines comply with A) Euro-3 B) Euro-4 C) Euro-5 D) Euro-6

    Show Answer Correct Answer: A Explanation: Stage-IIIA emission standards in track machine engines are roughly equivalent to Euro-3 emission norms.

  11. Vande-Metronom TRC can record track geometry at a maximum speed of A) 120 km/h B) 160 km/h C) 180 km/h D) 200 km/h

    Show Answer Correct Answer: C Explanation: The advanced Vande-Metronom Track Recording Car (TRC) can inspect track geometry at speeds up to 180 km/h.

  12. The 37° probe in USFD equipment is primarily meant to detect A) Transverse head crack B) Bolt-hole crack C) Web lamination D) Foot fatigue

    Show Answer Correct Answer: B Explanation: The 37° angle probe in Ultrasonic Flaw Detection is specifically oriented to detect defects and cracks around the bolt holes in the rail web.

  13. Mobile Flash-Butt Welding Units normally need electrical power of about A) 100 kVA B) 200 kVA C) 400 kVA D) 800 kVA

    Show Answer Correct Answer: C Explanation: Mobile Flash-Butt Welding plants are highly power-intensive and require an electrical power supply of approximately 400 kVA.

  14. Which of the following is NOT a function of Ballast Regulating Machine? A) Shoulder cleaning B) Sleeper insertion C) Boxing ballast D) Profile correction

    Show Answer Correct Answer: B Explanation: Sleeper insertion is a function of a sleeper laying machine or manual labour, not a Ballast Regulating Machine (BRM).

  15. Present Vision-2024 target is to keep one tamper for every ___ km of track. A) 100 B) 125 C) 150 D) 175

    Show Answer Correct Answer: B Explanation: The current maintenance target (Vision 2024) is to maintain a ratio of one tamping machine for every 125 km of track length.

  16. Rail-milling train achieves metal-removal accuracy of A) 0.02 mm B) 0.1 mm C) 0.2 mm D) 0.5 mm

    Show Answer Correct Answer: C Explanation: Rail milling provides a high precision finish, capable of removing metal accurately to approximately 0.2 mm.

  17. Mission Track was launched in A) 2005 B) 2007 C) 2012 D) 2016

    Show Answer Correct Answer: B Explanation: The “Mission Track” initiative, aimed at modernizing track maintenance practices, was launched in 2007.


Remember: Track machines are high-investment, high-technology assets – their productive deployment is key to achieving 160/200 km/h speeds and 30 t axle-load freight corridors. Expect at least 3-4 questions every year across RRB-JE/NTPC/Group-D papers.