Welding Methods
Welding Methods – Indian Railways Perspective
1. Why Welding Matters on Railways
- 94 % of Indian Railways’ 68,000 route-km is welded track (LWR/CWR) → eliminates fish-plated joints, reduces maintenance & ride noise.
- Welded turnouts, bridges, wagons & coaches → 30 % lighter, 40 % stronger than riveted structures.
- Welding defects → cause 17 % of rail fractures (Railway Board Safety Report 2022) → hence welding is a Category-A skill for JE/ALP/Technician.
2. Rail Steel Chemistry (to be welded)
| Element | IS:90 (52 kg), IRS-T-12 (60 kg) |
|---|---|
| C | 0.65–0.80 % |
| Mn | 0.90–1.30 % |
| Si | 0.15–0.30 % |
| P & S | ≤ 0.035 % |
| UTS | 880–980 MPa |
| Hardness | 260–300 BHN |
High carbon & alloy → hardenability & crack sensitivity → governs welding procedure.
3. Classification of Welding Processes used on IR
A. Fusion Welding (melts base metal)
- Gas Pressure Welding (GPW) – Thermit® process (Alumino-thermic)
- Electric Arc Welding
- SMAW (Manual Metal Arc) – electrodes: AWS E11018-M
- GMAW (MIG/MAG) – ER90S-G wire, Ar+20 % CO₂
- FCAW – AWS E91T1-K2
- SAW – Submerged Arc (turnouts, bridges)
- Flash-Butt Welding (FBW) – mobile & fixed plants
- Electro-slag / Electro-gas – thick web crossings
- Laser, Plasma, EBW – Metro & LHB coach body (stainless steel)
B. Solid-State Welding (no melt)
- Friction Welding – Alstom LHB wheel-axle
- Explosive Welding – transition joints for aluminium roof to steel body
4. Thermit (Gas Pressure) Welding – Most Asked in Exams
- Invented 1895 – Hans Goldschmidt – first rail weld 1899 in Germany; India 1928 on GIPR.
- Reaction:
3 Fe₃O₄ + 8 Al → 9 Fe + 4 Al₂O₃ + 3.2 MJ kg⁻¹ (Temp ≈ 2,400 °C) - Standard portion: 450 g Fe₃O₄ + 90 g Al + 15 g Ni & Cr = One crucible for 60 kg rail.
- Pre-heat temp: 900–1,000 °C (cherry red) – measured by optical pyrometer or Tempilstik° 980.
- Gap kept: 25 mm ± 1 mm (Indian Railways Permanent Way Manual 2021).
- Alignment tolerance: vertical ≤ 0.5 mm, lateral ≤ 0.3 mm.
- Upset metal (weld collar) projection: 3–5 mm each side.
- Cooling: 6 min natural + 10 min sand covering → only then traffic at 10 km/h; full speed after 1 h/30 °C temp fall.
- Acceptance test:
- USFD 100 % (2 MHz probe)
- Transverse tensile ≥ 720 MPa
- Bend 120° on 1.5 m mandrel without crack
- Hardness survey ≤ 350 HV in HAZ
- Defect rate target: ≤ 2 % (RB’s “Zero-Weld-Failure” drive 2023).
Recent IR initiative
- Auto-Thermit kit (RDSO 2017) – crucible pre-loaded, exothermic start by remote → reduces fume exposure to welders.
- Green-thermit – 30 % lower Al, Fe₃O₄ sourced from spent mill-scale → saves 1.2 t CO₂ per 1,000 welds.
5. Flash-Butt Welding (FBW) – Factory & SFW Pads
- Kaiser’s 1924 patent; Indian Railways first plant 1963 at Bhilai Steel Plant.
- Principle: Joule heating I²Rt + forging upset 6–8 mm.
- Parameters for 60 kg rail (UIC-60):
- Flash voltage: 3–6 V
- Current: 55–65 kA
- Upset force: 450 kN
- Total cycle: 120–150 s
- Heat-affected zone (HAZ) width: 25–30 mm (half of Thermit).
- Standards: IRS-T-18-2019 (provisional) & EN 14587-2.
- NRC (Greenfield) & RRTS “KAVACH” corridors: 100 % FBW rails.
- Mobile Flash-Butt Welding Plant (RDSO 2022) – 25 t self-propelled – can do 60 welds/day on running track → reduces possession time by 70 %.
6. SMAW & GMAW for Rolling Stock
- Electrode for freight wagon (IRSM-44 steel): AWS E7018 (4 mm Ø) – 160 A DC+.
- LHB coach shell (Stainless steel 301LN): GMAW-Short Circuit, 1.2 mm ER308LSi, 24 V, 180 A, 60 % Ar + 30 % He + 10 % CO₂.
- WPS qualified as per IS 7310 Part 1 & AWS D1.1/D1.6.
- Welder certification: BIS-5284 (earlier CITI) – valid 2 years, 6-month renewal test.
7. Defects, Symbols & NDT
| Defect | Cause | NDT | Accept limit |
|---|---|---|---|
| Lack of penetration | Low pre-heat | USFD | Zero |
| Slag inclusion | Fast travel | Radiography | ≤ 3 mm any dir. |
| Porosity | Moist electrode | UT/X-ray | ≤ 2 % area |
| Undercut | High current | MPI | ≤ 0.5 mm deep |
| Cold shut (Thermit) | Mis-alignment | UT | Not permitted |
8. Safety & Environmental Stats
- IR employs ~22,000 certified welders (2023).
- “Weld-Cloud” app (CRIS 2021) – geo-tagged every Thermit weld, uploads temp & USFD report → failure-analysis database.
- Hex-Chrome exposure limit (GMAW on SS): 0.05 mg m⁻³ (Factories Act 2020).
- Fire risk: Thermit crucible temp > 2,000 °C – mandatorily carried out in “Weld-Zone” 5 m clear of timber sleepers; water buckets & 2 DCP extinguishers kept.
9. Historical Timeline (Memory tip)
- 1895 – Goldschmidt invents Thermit
- 1928 – First Indian rail weld (GIPR)
- 1963 – Bhilai FBW plant
- 1998 – LWR made mandatory on BG
- 2010 – RDSO approves SKV-E (improved) mould
- 2017 – Auto-Thermit kit
- 2020 – Mobile FBW plant trials
- 2022 – RDSO permits “Wide-gap Thermit” (up to 60 mm gap) for repair
10. Future / Recent Updates (2023-24)
- “Friction-Stir Welding” of 6061-T6 aluminium roof panels – successful trial at Rail Coach Factory, Kapurthala – 40 % joint strength ↑, no fumes.
- “RailBot-W” – under development by DMRL & IR – AI-guided “narrow-gap laser-MAG hybrid” for field welds; expected 2026.
- Green-Hydrogen instead of Acetylene for gas pre-heating (IROAF pilot) → 2.5 kg CO₂ saved per weld.
15+ Railway-Exam MCQs on Welding Methods
-
Which reaction mixture is used in Thermit welding of rails? A) Fe₂O₃ + Al B) Fe₃O₄ + Al C) FeO + Al D) Fe + Al₂O₃
Show Answer
Correct Answer: B Explanation: The reaction mixture used in Thermit welding of rails typically consists of Iron Oxide (Fe₃O₄) and Aluminum (Al) powder. -
The pre-heating temperature required before pouring Thermit metal is about A) 600–700 °C B) 700–800 °C C) 900–1,000 °C D) 1,100–1,200 °C
Show Answer
Correct Answer: C Explanation: Rail ends must be pre-heated to approximately 900–1,000 °C to ensure proper fusion with the molten Thermit steel. -
Standard gap kept between rail ends during Thermit welding is A) 25 mm ± 1 mm B) 20 mm ± 1 mm C) 30 mm ± 1 mm D) 15 mm ± 1 mm
Show Answer
Correct Answer: A Explanation: A standard gap of 25 mm ± 1 mm is maintained to allow the molten metal to flow and fuse the rail ends effectively. -
Which welding process gives the smallest HAZ (Heat Affected Zone) width on rails? A) Thermit Welding B) Gas Pressure Welding C) Arc Welding D) Flash-Butt Welding
Show Answer
Correct Answer: D Explanation: Flash-Butt Welding uses intense localized heating and pressure, resulting in the narrowest Heat Affected Zone compared to other methods. -
The first rail weld in Indian Railways was carried out in the year A) 1910 B) 1928 C) 1947 D) 1952
Show Answer
Correct Answer: B Explanation: History records the first instance of rail welding on the Indian Railway system in 1928. -
Current required for Flash-Butt welding of 60 kg UIC rail is approximately A) 25–35 kA B) 40–50 kA C) 55–65 kA D) 70–80 kA
Show Answer
Correct Answer: C Explanation: To achieve the necessary heat for a 60 kg UIC rail section, a high current in the range of 55–65 kA is required. -
Which electrode is recommended for welding IRSM-44 freight wagon underframe? A) AWS E7018 B) AWS E6013 C) AWS E6011 D) AWS E8018
Show Answer
Correct Answer: A Explanation: AWS E7018 is a low-hydrogen carbon steel electrode commonly used for high-quality structural welding in railway wagons. -
The minimum transverse tensile strength accepted for a Thermit weld joint is A) 600 MPa B) 720 MPa C) 850 MPa D) 900 MPa
Show Answer
Correct Answer: B Explanation: As per standard specifications, a Thermit weld must exhibit a minimum transverse tensile strength of 720 MPa. -
Which NDT technique is mandatory for 100 % inspection of field Thermit welds? A) Magnetic Particle Inspection B) Radiography C) USFD (Ultrasonic Flaw Detection) D) Dye Penetrant Test
Show Answer
Correct Answer: C Explanation: USFD is the mandatory non-destructive testing method used to detect internal flaws in Thermit welds on Indian Railways. -
Upset force applied during Flash-Butt welding of 60 kg rail is about A) 200 kN B) 300 kN C) 350 kN D) 450 kN
Show Answer
Correct Answer: D Explanation: An upset force of approximately 450 kN is applied to forge the rail ends together during the final stage of Flash-Butt welding. -
Which of the following gases is NOT used in GMAW of stainless-steel coach body? A) 100 % CO₂ B) Argon + 2% O₂ C) Argon + CO₂ mix D) Pure Argon
Show Answer
Correct Answer: A Explanation: 100 % CO₂ is not used for stainless steel as it causes excessive spatter and undesirable carbon pick-up in the weld pool. -
Auto-Thermit kit introduced by RDSO reduces A) Rail gap B) Fume exposure & start-time C) Welding temperature D) Cost of Al powder
Show Answer
Correct Answer: B Explanation: The Auto-Thermit system is designed to improve safety by reducing worker exposure to fumes and decreasing the overall process start-time. -
The “RailBot-W” project under IR aims to use which advanced welding technology? A) Plasma Arc Welding B) Friction Stir Welding C) Laser-MAG hybrid welding D) Electron Beam Welding
Show Answer
Correct Answer: C Explanation: RailBot-W is a research initiative focusing on the automation of rail welding using Laser-Metal Active Gas (MAG) hybrid technology. -
Which defect is most likely with inadequate pre-heating in Thermit welding? A) Lack of penetration B) Slag inclusion C) Porosity D) Shrinkage cavity
Show Answer
Correct Answer: A Explanation: Inadequate pre-heating prevents the rail ends from reaching the fusion temperature, leading to a “lack of penetration” or “cold lap” defect. -
Permitted hardness in Heat-Affected Zone (HAZ) of rail Thermit weld is A) ≤ 250 HV B) ≤ 350 HV C) ≤ 450 HV D) ≤ 500 HV
Show Answer
Correct Answer: B Explanation: To prevent brittleness, the hardness in the Heat-Affected Zone of a Thermit weld is generally restricted to 350 HV or less. -
Mobile Flash-Butt Welding Plant can complete how many welds per day on running track? A) ~20 welds B) ~40 welds C) ~60 welds D) ~100 welds
Show Answer
Correct Answer: C Explanation: High-efficiency mobile plants are capable of performing approximately 60 welds per day depending on traffic blocks. -
Which organization developed the “Weld-Cloud” app for Indian Railways? A) RDSO B) RITES C) RVNL D) CRIS
Show Answer
Correct Answer: D Explanation: The Centre for Railway Information Systems (CRIS) developed the Weld-Cloud application for digital monitoring and data logging of welds.